Carl Deckard wrote:

> I respond:
>
> Unrealistic expectations may be more of a factor in the acceptance of
> tooling via RP&M than a mismatch between capabilities and true
> requirements. Ask yourself:
>
> 1) Do I really need plus or minus 0.0002 inch (0.005 millimeter)?
>

Plus or minus 0.0002 inches is a tight tolerance indeed. We have been
inspecting tooling and parts on CMM's for ten years. I can tell you first hand
that even the most carefully machined parts will meet this spec. only on very
rare occasions. In the case of a complicated 3D parting line, the drawing may
ask for these tolerances and the machinist may claim to have delivered, but
verification can be the trickiest part.

-- 
Steve Farentinos
PML, Inc.
201 W. Beach Ave.
Inglewood, CA 90302
310 671-4345
310 671-0858 Fax
310 671-1862 BBS